Contract Details:

Contract Value:

£ 176,643.87

Contract Duration:

12 Weeks: January to May 2015

Client:

Renfrewshire Council
Cotton Street,
Paisley, PA1 1JD
Frank Farrell

Quantity Surveyor:

Renfrewshire Council
Tom Scott

Contract Administrator:

Ross McGinn

Contract Type:

SBC/XQ/SCOT

Key Features:

  • Site Set Up/Clearance
  • Locating existing Services & CCTV Survey
  • Install Temporary Fencing and Barriers
  • Remove Concrete Edging and Kerbing
  • Excavations & Disposals
  • Street Lighting Works
  • Drainage Works including adjustment of drains connections and chambers and gullies
  • Geotextile Membrane, Backfill, Imported Fill
  • Surface Treatment / Type 1
  • Bituminous Surfacing, Regulating & Tack Coat
  • Reinstatement, Concrete & Concrete Paviors
  • New Kerbing and Edging
  • Traffic Signage / Road Markings
  • Soft Landscaping including Topsoil and Seeding
  • Removal and installation of Underground overspill water tank

Bus Parking Bay and Parking Spaces, Linwood On-X

Description of Works

Caley Construction Ltd were Appointed as Principal Contractor by Renfrewshire Council to Construct a New Bus Drop Off and Parking Area within the existing Linwood Community Sports Hub Site.

The works involved were the construction of a Bus Parking Bay and Additional Car Parking with Footpaths, Drainage and Street Lighting at the Linwood Community Sports Hub in Linwood, also known as Linwood On-X.

Key Supply Chain Members

Sub-Contractors     Suppliers
Pheonix Specialist Solutions – Road Markings Keyline – Building Supplies
Tarmac Limited – Surfacing Marshalls – Paving / Kerbs
Campbell & Kennedy – Electrical PDM - Drainage

 

DSCF3570
DSCF3922
DSCF3924
DSCF3925
DSCF3926
DSCF3927
DSCF3932
DSCF3933
DSCF3934
DSCF3935
DSCF3936
Entrance & Play Park
Pathways

Designed and built by Mucky Puddle