Contract Details:

Contract Value:

£ 209,034.68

Contract Duration:

12 Weeks March – June 2015

Client:

Glasgow City Council
231 George Street
Glasgow, G1 1RX
Contact: Aiden O’Meara

Contract Type:

NEC3 ICE CoC

Key Features:

  • Site Set –up / Clearance / Traffic Management
  • Install temporary barriers / fencing / signage
  • Vegetation Clearance including tree cutting
  • Demolition of Structures
  • Removal of Slabs / Kerbs / Fencing
  • Removal of Containers / Heating Units / CCTV Cameras
  • Removal of Chamber Covers and Frames
  • Removal of Street Furniture
  • Excavations / Disposals / Backfilling / Imported Fill
  • Surface Treatments / Geotextile Membrane
  • Type 1 / Bituminous Surfacing
  • Regulating / Tack Coat
  • Reinstatement / Concrete / Kerbing
  • Street Lighting Installation

Bellahouston Site Clearance & Prince and Princess of Wales Hospice Enabling Works

Description of Works

Caley Construction Ltd were appointed as Principal Contractor to carry out the Bellahouston Site Clearance Works by Glasgow City Council.

The project works involved site clearance of a current Glasgow City Council Bellahouston Park Plant Nursery complex, including the removal of anticipated asbestos material and the construction of new entrance to the walled allotment garden, together with the installation of street lighting.

Works included the demolition of buildings (brick and steel including removal of foundations), removal and disposal of commercial polytunnels, grubbing up and vegetation clearance, service disconnection and supply, street lighting installation, general site clearance including excavation in hard and recycling of hard material through crushing and planning.

Sub-Contractors

Demolition Works – RJM (Scotland) Ltd
Electrical Works – Edmiston Brown Ltd